We hereby confirmed our previous instruction for SC to proceed with the following works:-
1. To provide brickwork with plastering and pain finish for termination at gridline H/6D
level 3F, 4F, 5F
2. To omit roller shutter at level 2F gridline H/2D, J/2D, J/7D
3. To provide brick wall with plastering and paint finish to flush staircase at level 2F
gridline H/2D, J/2D, J/7D
SC is required to liaise with QS for assessment of associated variation cost.