Instructions :
Clause 11.0 Further to site walk on 17.10.16, we hereby confirmed for SC to proceed with the following work:.
1. To modify staircase2,3,4 door from 2.4m(h) to 2.1m(h) to clear staircase landing at
at neccesary location, COW to site verify work done
2. To flip opening direction of staircase 2 door at gridline H-G/3D as per Bomba requirement
SC is required to liaise with QS for assessment of associated variation cost.