Ref : Your letter SINO/XMUP/WBSB/052/2016
Please note the program schedule supplied the 24 October was only for discussion ( see included ) successively
we had other meetings, site conditions and other factors we change some priority included this action.
Our plan is to start the steel in the 8 floor tomorrow the 14 November and target to complete by the 20
November.
If you have any question o need clarification please do not hesitate to contact me.